First Stack Foundation Complete
Work continues at the Warrick Power Plant. A major undertaking in April was pouring the foundation for the first of two new stacks that will be built as part of the strategic environmental project.
At 1:00 a.m. on Saturday, April 15th, work started to pour more than 2500 yards of concrete. The work ended at 12:00 noon with more than 20 trucks rolling through each hour to keep the concrete running. The project included more than 100 employees from several regional contractors working a total of 1258 safe man-hours with no incidents, accidents or lost time injuries.
|
 |
|
|
 |