Alcoa Warrick Operations - Evansville
Power Plant Updates 
Warrick Power Plant Project Underway
Plans Set For Power Plant Foundation
First Stack Foundation Complete
Environmental Improvement Project Continues Making Progress
Warrick Power Plant Project Ahead of Schedule
First Stack Foundation Complete

Work continues at the Warrick Power Plant. A major undertaking in April was pouring the foundation for the first of two new stacks that will be built as part of the strategic environmental project.

At 1:00 a.m. on Saturday, April 15th, work started to pour more than 2500 yards of concrete. The work ended at 12:00 noon with more than 20 trucks rolling through each hour to keep the concrete running. The project included more than 100 employees from several regional contractors working a total of 1258 safe man-hours with no incidents, accidents or lost time injuries.

Copyright © 2008 Alcoa Inc.
country sites

customer login