January 15, 2010

Public Meetings January 18-21 to Provide Update on Proposed Greenland Aluminium and Hydroelectric Development Project

Public meetings will be held in Nuuk, Maniitsoq, Sisimiut, and Kangerlussuaq the week of January 18, 2010 to enable Greenland Development and Alcoa to report on their progress toward the establishment of a world-class aluminium smelter in Greenland and to seek questions and comments on the proposed project from interested parties. These meetings are a continuation of the self-rule government’s public meetings the week of January 11.

ERM, the consultancy that is preparing environmental impact assessment (EIA) for the proposed project, and their study partners will present the preliminary results of the baseline EIA studies and outline the next steps in the EIA process. The presentation materials for the meetings will be available at www.aluminium.gl and www.alcoa.com/greenland/en/proposed_smelter/meetings.asp.
The public meeting in Maniitsoq will be broadcasted live by KNR Radio.

The agenda for the meetings includes:
  • Update on project-related studies and activities from Greenland Development, Alcoa, the municipalities, and ERM;
  • A question-and-answer session for project- and EIA-related comments and questions; and
  • An open house session with information tables for each study topic. Study experts will be available at each table to answer questions.

The meeting schedule is as follows:

Nuuk
18th January, 2010
Place: Katuaq
Time: 19:00 – 21:30
Maniitsoq
19th January, 2010
Place: Public Hall
Time: 19:30 – 22:00
Sisimiut
20th January, 2010,
Place: Taseralik
Time: 19:00 - 21:30
Kangerlussuaq
21st January 2010
Place: Qinnguata Atuarfia
Time: 19:00 – 21:30

Contacts:
Greenland Development A/S
Ellen Christoffersen
Direct ph.: +299 482672

Alcoa Inc.
Kristján Halldórsson
Direct ph.: +299 533767
E-mail

Qeqqata Kommunia
Birte Engelsen
Direct ph.: +299 555510